Friday, April 2, 2021

Construction week 2-3

Last week blocks were laid to build up the floor

  The plumber and electrician laid out the pipes for 

    the first floor.
                                            and the form boards were added so the first floor

                                              could be poured. 

                                            Monday they were able to get the first floor poured
                                              Tues & Wed. this week they started to block up

                                                the 1st floor walls.

                                             Both this week and last were "short" weeks. Last week

                                              was a 4 day work week (because of covid lockdown)

                                              and this week was only a 3 day work week (because of

                                             the Holiday weekend and covid lockdown). Next week

                                              is hopefully the last "short" week we have because of

                                               the lockdown. They are working so hard and I am beyond

                                               grateful for the progress that has been made.
 